Project Record · WQ-2024-036Projects
Low-Voltage Systems Upgrade for a Hotel Chain
Guest-room control, access control, networking, and four floors of server-room cabling; acceptance passed at first review.
- Client
- Hotel chain · smart low-voltage
- Site
- Nancheng, Dongguan
- Scope
- Guest-room control / access control / network / 4-storey cabling
- Lead time
- 45 days
Quick summary
- Site/client: a 168-room hotel in Nancheng, Dongguan, undergoing a full refit.
- Scope: guest-room control, access control, guest and public-area networks, plus four floors of machine-room cabling and labelling.
- Lead time: 45 days; key decision: settle the labelling system before pulling cable, and separate guest, public and office networks.
- Outcome: all 168 rooms powered and tested individually, with link tests sampled by floor; excludes fire, lifts, AV and furniture.
Intelligent building services for a hotel chain in Nancheng, Dongguan: guest-room control, access control, networking and cabling for four equipment-room floors. (Guest rooms: 168 · Delivery: 45 days · Accepted at first review)
Context
A 168-room hotel refurbishment had guest-room control, access control, network and CCTV split across contractors, each pulling its own cabling, with four floors of unlabelled server-room infrastructure. The owner wanted one handover and one accountable party before opening.
Scope and exclusions
Guest-room control, access control, guest and public-area network, plus cabling and labelling for the four-floor server room. Fire systems, lifts, AV equipment and furniture were excluded.
- Included: in-room RCU control, door locks and key-card power linkage, AP placement and cabling
- Included: racks, patch panels, labelling scheme and as-built test records
- Excluded: fire alarm, lift intercom, TV and AV systems
Approach and key decisions
The decisive choice was to fix the labelling scheme before pulling cable. Refurbishments fail at acceptance when nobody can find a cable, so every run is coded floor-room-function with patch panels matching faceplates, handed over as a searchable register.
- Cabling and commissioning staged by floor so crews never wait on each other
- Three logical networks — guest rooms, public areas, back office — so guest devices never share a segment with management terminals
Deliverables and acceptance
As-built drawings, point and pair registers, server-room patching table, scene configuration list and test records. Acceptance combined room-by-room power-up tests with sampled link tests.
- Deliverables: as-built drawings, pair register, scene config, test report
- Acceptance: all 168 rooms tested individually; link tests sampled per floor
Common questions
Q: Why settle labelling before cabling?
A: The biggest refit risk is not being able to find a cable at acceptance. A floor-room-function code makes every patch panel and outlet traceable, so handover is a ledger rather than a bundle of cables.
Q: How is the 45-day programme sequenced?
A: Cabling crews enter first, commissioning follows floor by floor, then every room is powered and tested before link tests are sampled by floor.
Q: Why three separate networks?
A: Guest, public-area and office traffic are isolated so guest devices never share a segment with management terminals, and rate limiting or fault isolation stays simple.
FAQ
Frequently asked questions
- 01Why define labelling before cabling in a hotel?
- AnswerThe biggest risk in a retrofit is not being able to find a cable. A three-part code of floor-room-function, matched between patch panel and faceplate, delivers a searchable record rather than a bundle of cables.
- 02How were the 45 days organised?
- AnswerThe cabling crew went in first and the commissioning crew followed floor by floor. Each room was powered and tested before link tests were sampled by floor, so the two teams did not wait on each other.
- 03Why three separate networks?
- AnswerGuest rooms, public areas and offices are isolated on three logical networks. Guest devices never share a network with management terminals, and rate limiting and fault isolation are simpler later.
NEXT · WHAT HAPPENS AFTER
Need an assessment for a similar site?
We survey site points, cabling and power first, then quote the design, bill of materials and installation boundary.