Project Record · WQ-2023-026Projects
Cleanroom Access Control and Surveillance
Access control and monitoring for a cleanroom production area in an electronics plant.
- Client
- Electronics manufacturing · cleanroom
- Site
- Chang'an, Dongguan
- Scope
- 42 access points / air-shower linkage / personnel trace
- Lead time
- 26 days
Quick summary
- Site/client: an electronics factory cleanroom in Chang’an, Dongguan.
- Scope: 42 access points, ESD gates, air-shower linkage, cleanroom-level zoning and 90-day personnel trace.
- Lead time: 26 days; key decision: no entry without ESD test or air shower, with logged temporary access for visitors.
- Outcome: unauthorised passage blocked and personnel trace recoverable to point and time.
- Boundaries: excludes environmental monitoring, FFU/HVAC control and MES workstation binding.
Access control and surveillance for a cleanroom production area at an electronics plant in Chang'an, Dongguan, including anti-static turnstiles, air-shower interlocking and personnel movement records. (Access points: 42 · Delivery: 26 days · Movement records retained: 90 days)
Context
Cleanroom discipline is a matter of sequence: who entered which cleanliness zone, when, for how long, and whether the air shower was completed. The old access system only opened doors — no zoning, no trace.
Scope and exclusions
42 access points including anti-static turnstiles, air-shower linkage, zone grading and personnel trace retention. Environmental monitoring and line-equipment interlocks were excluded.
- Included: graded permissions, ESD-test-linked entry, no entry before completing the air shower
- Included: personnel trace queries with 90-day retention
- Excluded: FFU/HVAC control, particle monitoring, MES station binding
Approach and key decisions
Compliance steps were made hard constraints: a failed ESD test or an incomplete air shower keeps the gate closed, because a single bypass makes the whole record untrustworthy. A logged manual override remains for visitors and maintenance.
- Zones graded by cleanliness class with re-authentication on crossing; the trace records points, not just doors
- Visitors and maintenance use temporary grants with automatic alerts if they overstay
Deliverables and acceptance
Point maps, permission matrix, trace-query guide and operator training. Acceptance tested every point and reproduced violation scenarios (no air shower, no ESD test).
- Deliverables: point maps, permission matrix, trace accounts, training records
- Acceptance: violations must be blocked; traces must resolve to a specific point and time
Common questions
Q: Why block entry when the air shower is incomplete?
A: Compliance steps must be hard constraints. Any bypass makes the trace data untrustworthy and weakens cleanroom control.
Q: How do visitors and maintenance staff enter?
A: Through logged temporary access, with an automatic alert if they overstay. A manual path remains, but never an unrecorded one.
Q: Why record trace by point rather than by door?
A: Point-level records answer which cleanroom class was entered, how long someone stayed and whether the route was followed; a door event only shows that it opened.
FAQ
Frequently asked questions
- 01Why can nobody pass before the air shower is complete?
- AnswerA compliance step has to be enforced as a hard constraint. Leave one back door and the trajectory data is no longer trustworthy, and cleanroom management breaks down.
- 02How do visitors and maintenance staff get in?
- AnswerThrough temporary authorisation with a full record, and an automatic reminder if they overstay. A manual channel remains, but not unrecorded passage.
- 03Why record by point rather than by door?
- AnswerPoint-level records can answer which cleanroom class was entered, how long someone stayed and whether the prescribed route was followed. A door record only shows that a door opened once.