Project Record · WQ-2024-031Projects
Campus Security and PA System for a School
Perimeter surveillance, access control, and a campus-wide public address system.
- Client
- Private secondary school
- Site
- Dongguan (city level)
- Scope
- 124 camera points / zoned PA / one-touch alarm
- Lead time
- 38 days
Quick summary
- Site/client: a private secondary school in Dongguan with three teaching buildings, dormitories and two sports fields.
- Scope: 124 camera points, 16-zoned PA, one-touch alarm and role-based permissions.
- Lead time: 38 days; key decisions: role-based access and dormitory cameras positioned away from private angles.
- Outcome: zone-by-zone PA tests, point-by-point video checks and on-site alarm triggers.
- Boundaries: excludes recording classrooms, standardised exam rooms and off-campus road coverage.
Security and public-address systems for a private secondary school in Dongguan, covering three teaching buildings, the dormitory area and two sports fields, with one-touch emergency alarm. (Monitoring points: 124 · Delivery: 38 days · PA zones: 16)
Context
Campus security is less about cameras than about who may look, when, and how to raise an alarm. The school needed coverage of gates, corridors and sports fields, zoned public address, and a one-touch alarm at the guardhouse.
Scope and exclusions
124 camera points across three teaching buildings, dormitories and two sports fields, 16 PA zones and one-touch alarm. Classroom recording, exam-invigilation systems and off-campus pick-up areas were excluded.
- Included: camera points, server-room storage, PA zones and amplifiers, alarm linkage
- Included: role-based access (head teacher, security, dormitory staff)
- Excluded: recording classrooms, standardised exam rooms, street-side points
Approach and key decisions
Permissions were the critical design decision: dormitory staff see only their area, security sees the campus but cannot export, the head teacher can review everything. This was agreed before installation to avoid rework after handover.
- PA zoned by floor and outdoor area, with preset announcement templates for fire and exam scenarios
- Dormitory cameras positioned to avoid windows and private corridor angles, each location confirmed with the school
Deliverables and acceptance
Point maps, permission matrix, PA zone chart, alarm test records and training. Acceptance tested zone-by-zone audio, point-by-point images and the one-touch alarm.
- Deliverables: as-built drawings, permission matrix, zone table, test records, administrator training
- Acceptance: audible check per PA zone; alarm linkage verified by on-site triggers
Common questions
Q: How are school camera permissions separated?
A: Dormitory staff see only dormitory areas, security sees the campus without export rights, and the principal can review all records. Permissions are agreed before installation to avoid rework.
Q: How are dormitory privacy concerns handled?
A: Cameras avoid windows and private corridor angles, and every position is confirmed with the school rather than blanket-covered.
Q: What does 38-day acceptance check?
A: Zone-by-zone PA announcements, point-by-point video checks and on-site alarm triggers, not just a dashboard.
FAQ
Frequently asked questions
- 01How are campus camera permissions divided?
- AnswerDormitory staff see only dormitory areas, security sees the whole campus but cannot export, and the principal can review all recordings. Permissions are agreed with the school before installation, avoiding repeated changes after handover.
- 02How do dormitory cameras avoid privacy problems?
- AnswerAngles toward windows and private corridors are avoided, and each mounting position is confirmed with the school. There is no indiscriminate coverage.
- 03What is checked at the 38-day acceptance?
- AnswerLive PA announcements zone by zone, camera images point by point, and on-site triggering of the one-button alarm. Not just a dashboard review.