Project Record · WQ-2025-061Projects
Production Management System for a Precision Mold Manufacturer
Work-order dispatch, equipment inspection, and process traceability, integrated with the existing ERP material library.
- Client
- Precision mould manufacturing
- Site
- Chang’an, Dongguan
- Scope
- Work orders / inspection / traceability, integrated with existing ERP
- Lead time
- 46 days
Quick summary
- Site/client: a precision mould factory in Chang’an, Dongguan; scope: nine modules for work orders, inspection and process traceability.
- Lead time: 46 days; key decision: keep the existing ERP and add the shop-floor execution layer, with ERP as the master for material codes.
- Outcome: work-order nodes reduced from 11 to 7, flow time down 35%, inspection completion auditable.
- Boundaries: excludes ERP finance changes, machine PLC data collection and scheduling-algorithm optimisation.
A production management system for a precision mould maker in Chang'an, Dongguan, covering work-order dispatch, equipment inspection and process traceability, integrated with the existing ERP material master. (Modules: 9 · Delivery: 46 days · Work-order cycle time: -35%)
Context
The constraint was information, not machinery: work orders moved on paper so only the shop supervisor knew real progress, equipment inspections were signed on paper with no way to trace a miss, and process cards were not bound to batches — answering "when was this batch made" meant digging through files.
Scope and exclusions
Nine business modules, fourteen role permission sets, mobile work orders and inspections, and batch traceability queries. Replacing the ERP, financial accounting and machine-level PLC data capture were excluded.
- Included: dispatch and reporting, equipment inspection, station scanning, batch traceability, reports
- Included: two-way validation against the existing ERP material master
- Excluded: ERP finance changes, PLC acquisition, scheduling-algorithm optimisation
Approach and key decisions
The governing decision was to complement the ERP rather than replace it: material codes stay owned by the ERP, with a mapping table and two-way validation so two coding systems never run in parallel. Rollout used parallel running with on-site support instead of a weekend cutover.
- Work-order steps were reduced from 11 to 7 by merging approvals that produced no management action
- Scan-based inspection with overdue reminders turns "was it checked" into a record instead of a verbal confirmation
Deliverables and acceptance
Nine modules, a permission matrix, the ERP mapping table, inspection templates and training records. Acceptance used work-order cycle time and inspection completion, measured over four consecutive weeks after go-live.
- Deliverables: system and accounts, mapping table, operations manual, four-week operating report
- Acceptance: cycle time from work-order timestamps; completion from scan records against planned items
Common questions
Q: Why not replace the existing ERP?
A: The ERP remains the master for material codes, with a two-way mapping table for shop-floor use. Replacing it is slower and riskier; adding the execution layer first delivers more for less.
Q: How is the 46-day schedule organised?
A: Requirements and field mapping, work-order and inspection rollout, traceability and reporting, then parallel running with on-site support. Acceptance uses four consecutive weeks of live data.
Q: How is the 35% work-order flow reduction calculated?
A: From timestamp differences on work orders, comparing four consecutive weeks before and after go-live. It is not an estimate or a single-workshop sample.
FAQ
Frequently asked questions
- 01Why not replace the existing ERP?
- AnswerMaterial codes stay authoritative in the ERP, and the shop floor uses a mapping table for two-way validation. Replacing the ERP would be high-risk and slow; adding work orders, inspections and traceability first costs less.
- 02How were the 46 days scheduled?
- AnswerRequirements and field mapping, work orders and inspections, traceability and reporting, then parallel trial operation and on-site support. Acceptance uses four consecutive weeks of live data after go-live.
- 03How is the 35% drop in work-order handling time calculated?
- AnswerFrom work-order timestamps, comparing four consecutive weeks before and after go-live. It is not an estimate or a sample from a single workshop.